KATHMANDU: The initial unit of electricity from this project was integrated into the national grid last evening.
Located in Amachodingmo-5, Rasuwa, the project has the capacity to produce 42.5 megawatts of electricity.
The first unit of the electricity generated from Sanjen has been connected to the national transmission line after all technical tests were successfully completed, shared the project's sub-engineer, Robin Koirala.
Five megawatts of electricity were generated from one unit on Friday. Preparations are underway to test the remaining two units of the project and connect them to the central system by Sunday, said the company's CEO Arpan Bahadur Singh.
The company has stated that it is a model project among the semi-reservoir projects under construction in Nepal.
A 'peaking pond' has been constructed at the dam site of the Sanjen Upper Hydropower Project, which can store about 44,000 cubic meters of water.
By storing water from the pond additional electricity can be generated in the evening and the power house can be operated even in case of an emergency breakdown.