Tuesday Nov 5, 2024
Tuesday Nov 5, 2024

Rahughat Hydel Project 60% Complete in 14 Years


Nepalnews
RSS
2023 Sep 24, 15:20, Myagdi
PIC: GOOGLE

Fourteen years into construction, the under-construction 40-megawatt-capacity Rahughat hydropower project has seen 60 percent of construction work. The construction of the project was started in 2066 BS by the Nepal Electricity Authority (NEA) with a concessional loan of USD 67 million from Export Import Bank of India (Exim Bank) and joint investment of the NEA and the Government of Nepal.

After the contract with the old contractor, IVRCL, was terminated in 2072 BS due to the weak economic situation, the construction of the project advanced under the company's concept and engineering procurement and contract (EPC) format.

The project should have been completed in 2070 BS according to the previous schedule and agreement. The civil contractor Jaiprakash Associate (JP), which signed the contract of Rs 6 billion with the completion target being 2074 BS, has not been able to complete the project within the stipulated time.

 Overall 60 percent physical progress and 45 percent financial progress have taken place so far, said the project manager Raj Bista. "The project aims to operate from January, 2023. The contractor could not meet the completion target due to COVID-19 and other disasters. So, the contract agreement has been extended until 17 October, 2024," he said.

 The old contractor, IVRCL, did 10 percent of the work in eight years. The JP Company, which started works on construction of the access road in 2075 BS and a tunnel in 2076 BS, has so far constructed a 61-metre deep surge shaft, a 329-metre bottom pressure shaft, a 654-metre-long four access roads leading to the main tunnel and a 196-metre vertical tunnel.

Out of a six kms and 270 metres long tunnel, 5,162 metres have been completed so far. One thousand one hundred and eight metres of tunnel remains to be dug. ---


READ ALSO:

Rahughat Hydropower Project Nepal Electricity Authority (NEA) Export Import Bank of India (Exim Bank) IVRCL engineering procurement and contract (EPC) Jaiprakash Associate (JP) covid-19
Nepal's First Online News Portal
Published by Nepalnews Pvt Ltd
Editor: Raju Silwal
Information Department Registration No. 1505 / 076-77

Contact

Kathmandu, Nepal,


Newsroom
##

E-mail
nepalnewseditor@gmail.com

Terms of Use Disclaimer
© NepalNews. 2021 All rights reserved. | Nepal's First News Portal