Monday Nov 18, 2024
Monday Nov 18, 2024

Nagdhunga Tunnel digging halted for 20 days


Nepalnews
RSS
2023 Apr 05, 17:36,
The tunnel road has been expected to ease the traffic congestion seen along the Naubise-Nagdhunga section of the highway.

Digging work under the Nagdhunga Tunnel Construction Project in Kathmandu has been halted for 20 days after digging devices got damaged.

The Nagdhunga Tunnel Way Project said that earlier they used to dig 3 to 4 metres on average in a day but the digging has come to a grinding halt for 20 days owing to damages incurred in the machines used to dig the tunnel, shared Project Chief Nabin Man Shrestha.

Shrestha informed that although other project works were ongoing, the progress on the part of tunnel digging was slow. He divulged, "The soil in the digging site was substandard and machines getting damaged are recurring problems in the Project."

The first tunnel in the country measures 2.7 kilometres in length and has two lanes. The Project, for which foundation stone was laid in October, 2019, records 50.15 per cent physical progress so far.

Shrestha further said that the talks with the construction company Hazama Ando Corporation was ongoing as they have brought the matter to the knowledge of the Corporation entrusted with the construction of the Tunnel.

The Japanese construction company is reeling under human resources crunch and lacking adequate machines at present, it was said.

"The kind of rocks being unearthed while digging was different from the survey. Also, the rocks are coming out while diggings are different than estimated in the design of the Project," described Shrestha.

The tunnel is being constructed with the loan assistance of the government of Japan and is expected to reduce the time to clear Nagdhunga Pass to one-third of the current time and make transportation of people safe and efficient.

Furthermore, delays in addressing the compensation issues related to land acquisition were further pushing the deadline of the Project ought to be completed within 42 months from the start of the Project.

Workers falling sick, unavailability of machines and tools and other hurdles during COVID-19 pandemic slowed down the construction process in between.

Amid this, Dr Bijay Jaisi, Chief of Development Assistance Division under the Department of Road said that only digging work was halted while construction of other infrastructures in the Project continues.

READ ALSO:

Nagdhunga Tunnel Kathmandu Digging project Nabin Man Shrestha machines Hazama Ando Corporation Corporation entrusted construction Japan Land Acquisition COVID-19 pandemic Dr Bijay Jaisi
Nepal's First Online News Portal
Published by Nepalnews Pvt Ltd
Editor: Raju Silwal
Information Department Registration No. 1505 / 076-77

Contact

Kathmandu, Nepal,


Newsroom
##

E-mail
nepalnewseditor@gmail.com

Terms of Use Disclaimer
© NepalNews. 2021 All rights reserved. | Nepal's First News Portal