Saturday Nov 23, 2024
Saturday Nov 23, 2024

20 hour-long load shedding in Humla


Nepalnews
2021 Mar 12, 11:35, Simkot
Image: Google Maps

The district headquarters of Humla, Simkot, has been facing 20 hour-long load shedding for a long time.

Huge amount is spent every year to regulate the electricity supply, but the people here are bound to stay in dark.

During the winter, the Humla people suffer worst with load shedding all because of the sheer recklessness of employees at the Electricity Authority Office. The people here complain that most of the employees except the Office chief are the locals who are not capable to fix the problems. The load shedding is continued also because of unskilled employees.

The Simkot Office of the Authority has however said the power production was declined these days.

The industries at Simkot have been facing huge difficulty after the Hildum Micro Hydropower Project is imposing 20 hour-long outages. All furniture industries, electric shops and mobile shops have been closed due to this.

There are seven furniture industries at Simkot. Electric shop owner Nand Singh shared the plight that the shop was closed for long. "How long such problems go on? We need to run shop for earning livelihood," he wondered.

Sunmati Singh of Nand Mobile Centre said the mobile repair shop was closed due to power outage for long time. The electricity comes only for four hours- that too during night.

It is said more than three dozens of enterprises have been badly affected by the load shedding.

The students are also bearing the brunt of outage. Anjila Rokaya, an 8th Grader at Man Sarobar Secondary School, said, "It has been difficult for us to continue the study. We can't finish homework."

The students who have thronged Simkot for tuition classes for the SEE are worried much about 20 hour-long power outage.

District Hospital's senior ANM Sarita Bohara informed that all services that need electricity were disrupted at the hospital.

Distribution Centre Chief of Himdul Micro Hydropower Project Sajan Aidi said, "The project with the capacity of 500KW has now been producing only 140KW to 150KW electricity. It is the main reason behind increasing load shedding hours."

READ ALSO:

Humla Simkot Load-shedding Electricity Authority Office
Nepal's First Online News Portal
Published by Nepalnews Pvt Ltd
Editor: Raju Silwal
Information Department Registration No. 1505 / 076-77

Contact

Kathmandu, Nepal,


Newsroom
##

E-mail
nepalnewseditor@gmail.com

Terms of Use Disclaimer
© NepalNews. 2021 All rights reserved. | Nepal's First News Portal