Wednesday Apr 24, 2024
Wednesday Apr 24, 2024

Upgradation of Charikot-Jiri road section continues


Nepalnews
2021 Apr 13, 9:03, Dolakha
Image: Google

The upgradation work of Charikot-Jiri road section is taking place at a good pace with the completion of blacktopping up to Namdu bazaar. The construction company said that out of 55km, so far 22 kilometres has been blacktopped.

According to the construction company, almost 66 per cent of the Charikot-Jiri has been completed and the remaining tasks of blacktop will be completed within some months. "As the construction works are in full swing, the remaining part of blacktop will be completed in some months," Chairman of Baiteshwor Rural Municipality Chhabi Lama said.

A joint venture of Indian company Woodhill Infrastructure Limited and Nepal's Lama Construction Company had won the tender bidding of the project for the completion of 55 kilometres road by mid-August of 2021.

Rabindra Shrestha, Manager of Lama Construction Company, said that the project will be completed within the given deadline if the construction works continued at the current speed.

READ ALSO:

Dolakha Charikot Jiri Black Topping Construction Company
Nepal's First Online News Portal
Published by Nepalnews Pvt Ltd
Editor: Raju Silwal
Information Department Registration No. 1505 / 076-77

Contact

KMC-02, UttarDhoka,
Lazimpat, Nepal

Newsroom
+977–01–4445751 / 4445754

E-mail
[email protected] [email protected]

Terms of Use Disclaimer
© NepalNews. 2021 All rights reserved. | Nepal's First News Portal